How Councils Can Keep Services Running During a Software Changeover
For a New Zealand council, the final stage of a technologyone implementation is about keeping everyday work moving while staff switch systems. A supplier invoice might arrive after the old finance system closes, or a resident might call about a rates payment made that morning. A council preparing for a technologyone OneCouncil go-live can use those cases to decide what staff will do during the changeover, who will handle exceptions and which checks must pass before normal processing resumes.
Give each service a plan for the changeover
A cutover schedule should spell out when staff stop entering transactions in the old system and when they can start using the new one. That gap may be short, but each affected team needs to know what to do with work that arrives in the meantime. Accounts payable might record incoming invoices in a shared register. Customer service might continue taking enquiries while referring certain account updates to a designated officer.
The schedule should also account for work that crosses the cutover. A purchase order might have been raised and partly received before the changeover, with the balance due the following week. The receiving team should know where to record that delivery, and finance staff should be able to match the eventual invoice to the order. Walking through that example helps both teams agree on what information must carry across and who checks it.
Timing matters because the same interruption can have very different consequences from one week to the next. Finance and customer service teams can compare the proposed cutover window with the council’s own calendar, including rates instalment due dates, scheduled payment runs and month-end close. Staff availability matters too. A quiet weekend offers little advantage if the people who can resolve a payment or access problem are unavailable on Monday morning.
Rehearse the cutover with real working scenarios
A rehearsal should follow the planned sequence and give each team a chance to test its handover. For a rates payment, that could mean tracing a sample receipt from the point it is recorded through to the account balance a customer service officer sees. For a purchase order, the team could check whether quantities already received, the remaining balance and the correct supplier all appear together after migration.
The rehearsal can also expose dependencies that look straightforward on paper. A finance officer may be able to verify the opening balances only after another team confirms it has finished loading transactions. If the rehearsal takes longer than expected, the project team can adjust the timetable and identify which tasks can run at the same time. Recording who starts each check and who confirms it is complete makes the live sequence easier to follow.
Before go-live, council staff should agree on which problems would delay reopening a process. A missing historical attachment may have a workable solution if authorised staff can retrieve it elsewhere. An unexplained difference in opening balances requires a different decision. Naming the person who can make that call gives the teams a clear route to follow when time is tight.
Check how the first transactions move through the system
Once the new system opens, each team can check a small set of early transactions from start to finish. For finance, that might mean following the first supplier invoice from receipt through to approval. For customer service, it could mean confirming a recently recorded payment is visible to the staff who answer rates enquiries. Comparing what different teams see can reveal a problem that would be easy to miss if each team checked only its own step.
Any work logged during the changeover also needs an owner. A shared register can show which items still need to be entered, who entered them and when a second person checked them. That is particularly useful when an invoice or request has arrived through more than one channel. A quick review at the end of the first day can identify duplicate entries, unresolved issues and any work that needs to carry into the next morning.
Councils can prepare for go-live by rehearsing the cutover, checking open transactions and giving staff a clear process for handling exceptions.